Website : http://pdaipms.com/login.aspx

Obtain Completion or Occupation Certification :
Procedure :
** Application Form.
** Consent of bank from which loan is being raised.
** Attach self attested copy of allotment/re-allotment/change of ownership.

Application Format :

Application For Issuance Of Completion / Occupation Certificate

Property No. ______________________ Phase __________________
Name of Applicant ______________________________________________
Father’s / Husband’s Name ________________________________________
Address _______________________________________________________
Mobile ________________________________________________________
E-mail ________________________________________________________

Application For Issuance Of Completion / Occupation Certificate Check List :
i) Notice of completion & permission to occupy in Form B, as prescribed under rule 10(1) of the building rules alongwith a declaration by the owner.
ii) Certificate of completion issued by an empanelled Architect, of the Authority. List of empanelled Architects is attached.
iii) Photographs of the completed Building, to be pasted on the blanks pages and duly attested by the empanelled Architects.

Time Limit : 15 working days.

For Office Use Only :

Certified that I have checked and found all the documents in order.

Signature of Receipt Clerk
Name ____________________________
Date _____________________________

Signature of Superintendent
Name ____________________________
Date _____________________________

Notice of Completion and Permission to Occupy :

To
The Estate Officer
PDA
PUDA Complex
Urban Estate, Phase-II,
Patiala

Sir / Madam,

I/We hereby give you notice that the building / a part of the building described below and sanctioned with your order No. ____________________________________ dated ______________________ has been completed on ______________________ in all respects according to the provisions of the Punjab Regional and Town Planning and Development Act, 1995 and the rules made there under. The construction has been made as per the sanctioned plans and the suggested modifications have been carried out.

2. Completion Certificate from an empanelled Architect / Engineer who supervised the construction of the building submitted herewith.

3. Kindly permit me/us to occupy the building as required under Rule 11 of the Punjab Urban Planning and Development Authority (Building) Rules, 1996.

Description Of Building :

Type of Building : Booth / SCO / SCF / Indl. Site / Residential Plot / ____________________ Site No. ________________________ Phase __________________, Patiala.

Signature of the Applicant

Completion Certificate by an Empanelled Architect/Engineer

Form B {(See Rule 10(1)}

I do hereby certify that the following work (insert full particulars of work) has been supervised by me and has been completed to my satisfaction in accordance with the provisions of the Punjab Regional and Town Planning and Development Act, 1995 (P.A. No. 11 of 1995) and the rules made there-under as per sanctioned plans. The workmanship and the quality of material used in construction is as per building norms. That no provisions of the Punjab Regional and Town Planning and Development Act, 1995 (P.A. No. 11 of 1995) and the rules made thereunder and no requisition made, condition prescribed or order issued thereunder has been transgressed in the course of the work.

Particulars Of Work :

Type of Building : Booth / SSS / SCO / SCF / Indl. Site / Residential Plot / ___________ Site No. __________________Phase _____________________, Patiala.

Signature
(Empanelled Architect / Engineer)

Download Application Form Here :
https://www.indianjobtalks.in/uploads/13155-completion-and-permission-to-occupy.pdf

Time limit :
07 working days from the date of receipt of application.

Note :
In case, any citizen does not obtain the service within the given time limit, he may file an appeal in the office of the Additional Chief Administrator, PDA Patiala

Note : It would be preferred to print on A4 sheet.

Contact Us :
Patiala Urban Planing & Development Authority
Puda Complex
Urban Estate, Phase – Ii,
Patiala.

Leave a Reply

How to add comment : 1) Type your comment below. 2) Type your name. 3) Post comment.

IndianJobTalks © 2022

Contact Us   Privacy Policy   SiteMap